Before an ISO certificate is issued, an organisation goes through two audits. Many people treat them as one visit split over two days. In fact they have different purposes.
Stage 1: are you ready
The Stage 1 audit does not yet judge results. It checks whether the system is built in a way that makes the full audit worthwhile. The auditor reads the documented information, checks the scope, looks at whether an internal audit and a management review have been done, and speaks to the people responsible. At the end you receive a list of points to fix before Stage 2.
Stage 2: does it work in practice
Stage 2 takes place at your premises. The auditor does not only read documents but follows real processes. They talk to the people who do the work, ask to see records, look at production or the service and compare what they find with what was written. If a procedure says one thing and the work is done another way, it shows.
What counts as a finding
- major nonconformity: a requirement of the standard is not met in a way that affects the system's ability to deliver the intended results
- minor nonconformity: an isolated gap that does not undermine the whole system
- opportunity for improvement: an observation that is not a requirement but could strengthen the system
A major nonconformity has to be corrected and verified before certification is granted. For minor ones a corrective action plan is normally asked for.
How to prepare without the stress
Do not prepare only the documents. Talk to the people the auditor will ask and make sure they know what they do and why. Check that records exist and match the processes. Run the internal audit seriously, because it finds the problems before someone else does.
After Stage 2
Once the findings are closed, the audit report is reviewed by a person or committee that did not take part in the audit, and they decide whether certification is granted. It cannot be promised in advance, because it depends on what the audit finds.